Cabinetry
Count cabinets and specify construction, finish, internal fittings, trim and installation. A linear-foot figure alone is not a cabinet package.
2026 planning edition · Manhattan & Brooklyn
Plan your NYC kitchen or bathroom renovation with clear labor, materials and project-specific allowances.
2026 / Cost overview
| Project | Labor | Finishing materials |
|---|---|---|
| Kitchen | $27,000–$31,500 for the baseline scope, without a full electrical upgrade | From $27,000, excluding appliances; add 10% shipping and handling on MyHome-supplied materials |
| Bathroom | From $33,750; no fixed upper limit | Usually $10,800–$14,400; add 10% shipping and handling on MyHome-supplied materials |
Planning guidance reviewed September 2026. These figures depend on scope and selections. Materials are separate from labor. Applicable taxes, appliance purchases and other excluded costs must be added. A site visit and written proposal establish your project price.
Confirm exactly what your labor proposal and material schedule include. Count design, installation, trade permits, delivery and handling only once. Full-apartment projects require a tailored proposal.
Baseline kitchen labor is $27,000–$31,500 when a full electrical upgrade is not required. Wall removal, pass-through creation, larger kitchens, washer/dryer additions or updates, skim-coating and dropped ceilings increase the scope and price.
Allow an additional $13,500–$18,000 for a new or relocated panel and kitchen rewiring under a major electrical permit when required. This does not include a service upgrade from the building’s common hallway or basement electrical trough. Confirm requirements with the project’s licensed electrician.
Kitchen finishing materials start at $27,000, excluding appliances. Add 10% shipping and handling on MyHome-supplied materials. With a $27,000 material allowance and $2,700 handling, the baseline arithmetic is $56,700–$61,200 before appliances, electrical upgrades, other extras, applicable tax and contingency. This is a planning example, not an all-inclusive package or an upper limit.
Bathroom labor starts at $33,750. Larger rooms, separate tubs and shower stalls, full-height tiling throughout, very small or very large tiles, skim-coating and dropped ceilings require additional pricing.
If a panel upgrade and dedicated electrical line are required, allow approximately $9,000 more, subject to assessment. This allowance is not a universal permit rule or a quote for every building.
Finishing materials are usually $10,800–$14,400, plus 10% shipping and handling on MyHome-supplied materials. Using minimum labor, this gives $45,630–$49,590 before electrical upgrades, other extras, applicable tax and contingency. This variation reflects materials only; it is not a ceiling on bathroom renovation cost.
Both co-ops and condos can impose substantial requirements. Ask the managing agent for the current alteration agreement, fee schedule, insurance requirements and work rules before fixing the budget.
| Item | How to budget it |
|---|---|
| Application and professional review | Request the building’s actual fees and repeat-review charges. |
| Refundable alteration deposit | Show separately as cash tied up; return depends on the agreement and compliance. |
| Insurance documentation | Confirm required contractor coverage and endorsements with the managing agent and insurer. Do not assume a generic annual premium is payable by the homeowner. |
| Access and logistics | Confirm elevator bookings, protection, debris removal, permitted hours and work-duration penalties. |
| Wet-area changes | Confirm building-specific relocation restrictions before committing to a layout. |
The calculator applies no automatic co-op surcharge or condo discount. Enter only quoted extras that are not already included elsewhere.
Ask who provides and pays for each service. Design-build proposals can include some of these items; adding a generic percentage on top can double-count them.
Plumbing and electrical trade permits are assumed included in the quoted labor scope. DOB filing/work permits, related expediting, tenant protection planning and asbestos inspection are excluded when required; a preliminary allowance is $9,000–$13,500 for the package on many projects, subject to scope. Confirm all inclusions in writing and do not add fees already covered.
| Budget line | What to confirm |
|---|---|
| Design and professional services | Confirm included design services and any fee triggered by sourcing materials independently; price architect, engineering, survey, filing support and special inspections separately when required. |
| City approvals and closeout | Applicable application, trade, permit and inspection fees; completion and sign-off responsibilities. |
| Site investigations | Testing, investigation and any required remediation, based on the actual building and scope. |
| Purchases and deliveries | Applicable taxes, shipping, fabrication, handling, storage and long-lead-item costs. |
| Life during construction | Temporary housing, moving, storage and overlapping living costs. |
| Scope changes | Documented allowances and a written change-order process. |
NYC DOB: Do I need a permit? explains that most construction needs permits, with exceptions for some minor work. Your design professional and licensed trades should determine the filing route and fees. This guide does not apply a universal permit price.
Use written supplier quotes tied to quantities and specifications. Separate MyHome-supplied items from client purchases; add both to your budget. Check handling, storage, delivery, applicable tax and later material additions. Confirm whether each quote is supply-only or installed.
Count cabinets and specify construction, finish, internal fittings, trim and installation. A linear-foot figure alone is not a cabinet package.
Specify slab, measured area, fabrication, edge details, cutouts, delivery and installation.
Measure surfaces, allow for waste and confirm substrate preparation, waterproofing, trim and labor.
List exact models, panels, electrical or gas requirements, delivery and hookup.
Include valves, trim, drains, accessories, shower glass and fitting charges.
Include fixtures, controls, hardware, paint preparation and finish details.
Do not add these installed quotes in full if the labor proposal already covers the same work. Reconcile the two documents first.
| Phase | Planning task |
|---|---|
| 1. Define scope | Agree on rooms, layout, finish expectations and budget boundaries. |
| 2. Design and investigate | Measure, assess existing systems and finalize specifications. |
| 3. Building and city review | Confirm required submissions and review dependencies. |
| 4. Procurement | Check actual lead times before committing to a start date. |
| 5. Construction | Sequence demolition, rough-ins, inspections and finishes. |
| 6. Punch list and closeout | Complete corrections, required sign-offs and handover documents. |
Approvals, procurement and construction may overlap. Short room-level construction schedules do not represent the total elapsed project time. Ask for a project-specific schedule, including building work windows and long-lead materials.
Hidden damage, uneven floors and outdated services can alter the scope after investigation or demolition.
Utility moves, structural changes, HVAC and electrical capacity need separate assessment.
Custom fabrication, intricate tile layouts and specialty installation increase both material and labor requirements.
Access, working hours, occupied areas and review requirements affect scheduling and productivity.
Contingency is a reserve for uncertainty, not permission to proceed with unapproved extras. A known requirement belongs in the base scope.
Your inputs / Your scope
Choose a room and adjust the allowances to your written proposal. Bathroom labor starts at a minimum; the calculator cannot predict the upper cost of a larger scope.
No. Confirm scope, selections and existing conditions with MyHome. Bathroom labor is a starting minimum and kitchen labor excludes a full electrical upgrade.
Plumbing and electrical trade permits are assumed included in the quoted labor scope; confirm this in your agreement. DOB filing, a DOB work permit, related expediting, tenant protection planning and asbestos inspection are separate when required. Allow roughly $9,000–$13,500 for that package on many projects, subject to the actual scope and professional quotes. This is not a government permit-fee schedule.
MyHome’s published terms state that projects signed on or after April 1, 2026 qualify for its 10-year limited warranty; earlier projects have a 5-year term. Coverage and exclusions are governed by the applicable written warranty. Review eligibility and exclusions.
Pricing guidance reflects MyHome’s sales review in September 2026 and is intended for early planning. Scope, selections and existing conditions determine the written proposal. Worked examples are calculations, not completed-project averages. No full-apartment or competitor per-square-foot pricing is used.
Planning information only, not an offer, binding quote or guarantee. Actual pricing, timing, inclusions and warranty coverage depend on the written agreement, approved scope, building requirements and existing conditions. Appliances, applicable taxes, professional fees, DOB filings, remediation, temporary housing and other costs are excluded unless explicitly included or entered. A contingency does not cap project cost. Deposit refunds depend on the building’s terms.
Make it specific
Bring your priorities, building requirements and budget questions. We’ll help define the scope for your renovation.
Schedule a free consultation(212) 666-2888 · Midtown Manhattan showroom
Just a moment...