Tub to Shower Bathroom Renovation at 201 East 17th Street

Tub to Shower Bathroom Renovation at 201 East 17th Street

Designer Eran
Project manager Ofek
Renovation Expert Andrew Rooney

Projects › Lower Manhattan › 201 East 17th Street

Completed project · Lower Manhattan, New York, NY

A bathroom whose scope was reviewed three times by a professional engineer acting for the building, and got more demanding each round. The most useful document on this page is not a photograph: it is a 29-point letter setting out exactly what a New York apartment bathroom is allowed to do.

Renovated bathroom in large-format grey tile, with a sliding glass shower enclosure, stainless corner shelves, a white vanity with a black stone top and a live-edge wood shelf above the toilet
This began as a bathroom with a tub. The conversion to a shower was decided mid-review, and it changed what the building required.

Job record

Location
Gramercy, New York, NY 10003
Building
201 East 17th Street
Scope
Full bathroom renovation, tub converted to a walk-in shower
Review
Professional engineer’s review, three rounds, April to June 2022
Record
Photographed before and after
Filings
LAA plumbing permit, electrical permit, sign-offs to management at completion
Completed
2022

What was there before

These are the household’s own photographs, taken before anything was touched. They are worth looking at carefully, because almost every requirement in this project traces back to something visible in them.

The bathroom before the renovation, with a bathtub behind a curtain, a wall-hung vanity, a mirror with bulb lighting and dark textured wall paint
The starting point: a tub behind a curtain, in a room with no glass and no niche.
Looking down into the original bathtub, with square white wall tile above it and a worn tub floor
This tub is the reason the job needed a two-inch drain line and a permit.
The original bathroom floor in beige tile, with the toilet, the base of the vanity and a wooden threshold at the doorway
The old floor and saddle. Everything below this came out, down to the slab.

A bathtub behind a curtain. No glass, no niche, no recess of any kind, so storage was surface-fixed shelving screwed to the wall. Square white tile in the tub surround and beige tile on the floor, both original. A sink on exposed legs with the branch pipework running away behind a wall that had not been opened in decades.

The bathroom before work, seen from the doorway, showing the vanity, the mirror with its bulb lights, the toilet and the hallway beyond
The vanity and toilet positions were kept. Almost nothing else was.
The original vanity and sink beneath a mirror with bulb lighting, beside the shower curtain
A sink on exposed legs, with the branch pipework running behind the wall unchanged since the building went up.
Two narrow shelves fixed to the dark textured wall beside the shower curtain
Storage was surface-fixed shelving because there was no recess anywhere in the room.

The tub is the single most consequential thing in these pictures. Replacing it with a shower is what forced a larger drain line, which forced a decision about the structural slab, which produced the raised shower floor described further down. The scope did not start out proposing that: it began as a tub replaced in kind, and changed halfway through the review.

The shower curtain and rail with the mirror alongside, in the bathroom before work
A curtain rail spanning the tub is what a frameless glass enclosure replaced.
The mirrored wall of the original bathroom, reflecting the room and its lighting
The last picture taken before demolition began.

Twenty-nine conditions, and the ten-foot rule

This building sends alteration scopes to a licensed professional engineer. The first review came back in April 2022 as twenty-nine numbered points. Several of them are worth knowing whether or not you live in a building that does this, because they are the rules everyone is working to whether they say so or not.

The one with a number in it is the most useful. Plumbing work can be done without an alteration permit provided a master plumber files an Ordinary Plumbing Work report with the Department of Buildings’ LAA unit, and provided the job replaces less than ten feet of waste, water or vent piping. Cross that ten-foot line and an LAA permit has to be filed instead. Separately, if any wall is removed, modified or created, or any suspended ceiling installed, an alteration-type permit is required regardless.

The rest sets the standard of the work. All original branch water, drain and vent piping removed and replaced back to the riser shut-off valves and stacks. Properly rated bronze ball valves and check valves at all distribution lines, with fire-rated access doors so they can be reached. Flexible copper tubing not permitted, solid copper only, fully supported and thoroughly insulated, and no plastic supply piping at all. Exposed insulation stripped and replaced with paper-faced preformed fiberglass before any finish goes on.

The bathroom along its length, showing the glass shower enclosure, the vanity with its black stone top and a framed photograph on the far wall
Sliding glass on an exposed steel track, rather than a hinged door swinging into a narrow room.
The vanity and toilet seen past the open shower door, with the wood shelf running above the cistern and the tiled shower floor visible below
The shelf over the toilet is the only storage added. Everything else is in the vanity or on the shower shelves.

What the review would not let the scope get away with

Two points in that first letter are examples of a review doing the job a review exists to do.

Point ten notes that the scope clearly states branch lines are to be replaced, but that other line items say fixtures will be installed on existing rough-ins. Those two statements cannot both be fully true, and the ruling is that replacement of all branch pipes has to be performed. That is an internal contradiction in a document that had already been signed, caught by somebody reading it properly.

Point eleven deals with the niche and the recessed medicine cabinet, whose locations the scope had left to be determined. The review fills in the constraint: recesses can only be created on walls fully within the apartment, never on an exterior wall, a common wall or a hallway wall, never where they would disturb a plumbing line or a riser, fully waterproofed when they sit inside a shower, and always constructed so that the fire rating of the wall they are cut into is maintained. If you are planning a niche, that is the checklist.

The shower interior, with a rain head above, a handshower on the wall, two stainless corner shelves and a single control plate
A fixed rain head and a handshower, each on its own volume control.
Close view of the brushed nickel basin faucet against the black stone counter and the white integrated basin
The basin is integrated into the top, so there is no rim seam to fail.

The scope changed halfway, and the requirements changed with it

The original scope replaced the bathtub in kind: tub out, tub in. In the written response of May 2022 that changed to a tub-to-shower conversion, and the engineer re-reviewed on that basis a week later.

The new conditions followed immediately. Every new shower must have a waterproof pan. A licensed plumber must confirm that a two-inch drain line is available. Drain piping may not be replaced beyond the apartment, and the adjoining apartments must be protected from disruption. Waterproofing now has to run continuously from the bathroom floor through the shower and full height within the shower walls, and the lead pan must extend up and over the shower curb. A drawing showing the configuration of the shower floor had to be produced.

And then the condition that shapes what you can see in the photographs: increasing the size of the drain line must be achieved without channeling the structural slab, which, the letter notes, may require installation of a raised shower.

Close detail of the dark stone shower curb sitting above small-format square floor tile, against the large-format grey wall tile
The shower floor was built up rather than cut into the slab, which is what puts a step at the entrance.
Close view of the sliding glass door hardware, showing the steel track, the rollers and the glass panels below
The track carries the weight, so the glass has no frame around it.
The live-edge wood shelf above the toilet, its bracket fixings and the grey tile wall behind it
A single piece of timber on two brackets, set high enough to clear the cistern lid.

Why some showers have a step in them

A tub drain and a shower drain are not the same size. Converting one to the other usually means getting a larger drain line into a floor that was not built to take it, and in a concrete building there are only two ways to do that: cut a channel into the structural slab, or build the shower floor upward until the new drain fits above it.

Cutting the slab was refused. So the shower floor was built up and a step-in shower created, which MyHome confirmed in writing. The engineer then made one further demand, in a third review letter in June: the confirmation was not shown in the drawing, so the drawing had to be revised, and it had to show waterproofing at the concrete slab below the shower as well as the waterproofing inside the shower pan.

That third letter contains the single most useful detail in the whole file. The proposed drawing showed Laticrete 9235 running full height at the shower walls and Noble Seal beneath the bathroom floor, which is a perfectly normal pairing of two different products. The review insisted the drawing show that the two are directly connected to one another. Two good waterproofing systems that do not meet are a leak, and the place they fail is precisely the joint nobody drew.

What the crew did, in order

  1. Submit the scope and wait for the engineer

    The scope of work was dated 31 March 2022 and forwarded by the managing agent to a professional engineer. The review came back on 26 April as twenty-nine numbered conditions.

  2. Answer every point in the same numbering

    The response of 12 May addresses each of the twenty-nine in the same format, confirming them, and uses point two to change the scope from a tub replaced in kind to a tub-to-shower conversion. Point one is answered with a commitment to pull an LAA permit on the basis of the new scope.

  3. Take the second review on the new scope

    On 18 May the engineer re-reviewed. Points one and three through twenty-nine were accepted. Points two, seven and nine were reopened, because a shower is not a tub: waterproof pan, two-inch drain, no channeling of the slab, continuous waterproofing, lead pan over the curb, and a drawing of the shower floor.

  4. Draw the shower floor and get it sent back

    A shower detail was produced. The June review accepted that it showed waterproofing full height at the shower walls, and required two additions: that the drawing show the wall waterproofing directly connected to the floor waterproofing beneath it, and that it show the built-up, step-in shower floor that had been confirmed in writing but not drawn.

  5. Strip out and replace every branch line

    All original branch water, drain and vent piping removed and replaced back to the riser shut-off valves and stacks, in solid copper, fully supported and insulated, with bronze ball and check valves at the distribution lines and fire-rated access doors to reach them.

  6. Build the shower floor upward

    A waterproof pan, the floor built up to accept a two-inch drain without cutting the slab, and the lead pan carried up and over the curb.

  7. Waterproof floor and walls as one system

    Noble Seal beneath the bathroom floor, turned at least four inches up at the perimeter of each wall, and Laticrete 9235 full height within the shower, joined to one another rather than stopping short.

  8. Have the rough-ins examined before anything is covered

    The building’s engineer had to be given sufficient notice to examine all rough-ins, including branch pipes, valves, insulation and waterproofing, before any finishes were installed. No work at all until every required permit was posted on site.

  9. Tile, glaze and fit out

    Large-format grey tile through the room, small-format tile on the built-up shower floor, a sliding glass enclosure on an exposed track, stainless corner shelves, a vanity with an integrated basin in a black stone top, and a live-edge timber shelf above the toilet.

  10. Forward the sign-offs

    On completion, final sign-offs for each permit go to management, along with a copy of the plumbing report filed with the Department of Buildings.

Materials and finishes

Shower

ElementSpecification
ConversionBathtub removed and replaced with a walk-in shower
FloorBuilt up rather than channeled into the slab, creating a step-in shower
Drain2 in drain line, confirmed available by a licensed plumber; no drain piping replaced beyond the apartment
PanWaterproof lead pan, carried up and over the shower curb
EnclosureSliding glass panels on an exposed steel track
FittingsFixed rain head and handshower with separate volume controls
ShelvingStainless steel corner shelves

Waterproofing

ElementSpecification
Beneath the floorNoble Seal membrane, extended at least 4 in up each wall at the perimeter
Shower wallsLaticrete 9235, full height
JunctionWall and floor systems required to be directly connected, and shown so on the drawing
Below the showerWaterproofing at the concrete slab beneath the shower, in addition to within the pan

Plumbing

ElementSpecification
Branch linesAll original branch water, drain and vent piping replaced back to the riser shut-off valves and stacks
PipeSolid copper only, fully supported and thoroughly insulated; no flexible copper, no plastic supply piping
ValvesRated bronze ball valves and check valves at all distribution lines
AccessFire-rated access doors to all valves
InsulationExposed insulation removed and replaced with paper-faced preformed fiberglass
ToiletExisting rough-in retained for the lead bend and drain, inspected during replacement; supply line renewed

Fittings and finishes

ElementSpecification
Wall and floor tileLarge-format grey porcelain through the room; small-format tile to the built-up shower floor
VanityWhite cabinet with a black stone top and an integrated basin
FaucetBrushed nickel, deck mounted
ShelfLive-edge timber shelf on brackets above the toilet
Niche and medicine cabinetFramed only into walls fully within the apartment, fire rating maintained, fully waterproofed where within the shower

Filings and conditions

ElementSpecification
PlumbingLAA permit filed by a licensed plumber, on the basis of the tub-to-shower scope
ElectricalPermit obtained by a licensed electrician from the Department of Buildings
InspectionAll rough-ins examined by the building engineer before finishes
FirestoppingRequired at all openings created or exposed through slabs and fire-rated assemblies
RisersNot to be disturbed; probes opened to locate them before disturbing partitions
VentilationNot to be altered; no fan discharged into existing vents, no vent grills modified
Hazardous materialsAll materials for demolition tested for asbestos and lead before being disturbed
Sign-offFinal sign-offs for each permit forwarded to management on completion

Conditions are quoted from the three review letters prepared for the building by a professional engineer and from MyHome’s written response to them, all held in the job file. Materials are from the scope of work dated 31 March 2022 as revised.

The result

29conditions in the first review
3rounds of engineering review
10 ftof pipe, the line between a report and a permit

More MyHome projects in Manhattan

Questions this project answers

Do I need a permit to renovate a bathroom in NYC?

For the plumbing, it depends on how much pipe you replace. The engineering review on this job states the rule precisely: plumbing renovations can be performed without an alteration permit as long as a master plumber files an Ordinary Plumbing Work report with the Department of Buildings’ LAA unit, and only where the job replaces less than ten feet of waste, water or vent piping. Above that, a licensed plumber must file an LAA permit. Separately, if any wall is removed, modified or created, or a suspended ceiling installed, an alteration-type permit is required regardless of the plumbing. All electrical work needs a permit obtained by a licensed electrician. This job ended up pulling an LAA once the scope changed to a shower.

Why do some walk-in showers have a step up into them?

Usually because the drain could not be lowered. A shower needs a larger drain line than a bathtub, and in a concrete building you can either cut a channel into the structural slab to fit it or build the shower floor upward until it fits above the slab. On this job cutting the slab was expressly refused, and the review letter says so plainly: increasing the size of the drain line must be performed without channeling the structural slab, and this may require installation of a raised shower. So the floor was built up and a step-in shower created. If you are converting a tub to a shower in a concrete building, ask about the drain before you assume a flush threshold.

What is the most common place bathroom waterproofing fails?

The joint between two systems, and this project has the clearest statement of it. The shower drawing showed Laticrete 9235 running full height on the shower walls and Noble Seal beneath the bathroom floor. Both are sound products correctly specified. The engineer sent the drawing back anyway, requiring it to show that the wall waterproofing is directly connected to the floor waterproofing beneath it. Two good membranes that do not meet leave a gap exactly where water collects. When you review a waterproofing detail, look for the junction rather than the products.

Where am I allowed to put a recessed niche or medicine cabinet?

Only on walls that sit fully within your own apartment. The review here sets out the full constraint: recesses cannot be created on exterior walls, common walls or hallway walls; cannot be created where they would disturb any plumbing line or riser; must be fully waterproofed when they sit inside a shower; and must be constructed so the fire rating of the wall they are cut into is maintained. If the niche goes into a demising wall between two apartments, the fire rating has to be maintained there too. Confirm the wall before you design around the niche, because the location is not a finish decision.

What should I expect from a building engineer review of my renovation?

That it gets stricter, not looser, and that inconsistencies in your own paperwork will surface. This scope was reviewed three times between April and June 2022. The first review ran to twenty-nine numbered conditions and caught a contradiction in the signed scope, which said branch lines would be replaced in one place and that fixtures would go on existing rough-ins in another. The second review reopened three points because the scope had changed from a tub to a shower. The third sent back a drawing that was correct as far as it went but did not show how two waterproofing systems joined. Budget several weeks for this and write your scope so that it does not contradict itself, because somebody is going to read it line by line.

Planning something like this?

MyHome has renovated apartments, co-ops, condos and townhomes across Manhattan and Brooklyn for more than 25 years. Complete the short questionnaire to start an estimate.

Let’s design your home together

Complete the short questionnaire to kick off your estimation process

Get an Estimate

Recent Projects

Just a moment...