Kitchen Renovation and Wall Removal at 45 West 11th Street

Kitchen Renovation and Wall Removal at 45 West 11th Street

Designer Adam
Project manager Danny
Renovation Expert Adam

Projects › Lower Manhattan › 45 West 11th Street

Completed project · Greenwich Village, New York, NY

A Greenwich Village kitchen opened into the living area by taking out the wall between them, with the electrical panel moved, a new line run out to the island through the column, and eighteen inches of wood floor lifted so the tile could reach the island. Scoped at five to seven weeks.

Renovated kitchen in navy blue with brass hardware, opening onto a living area, with a white stone island and two wooden stools
The wall that used to divide this kitchen from the living area is gone. The island stands roughly where it ran.

Job record

Location
Greenwich Village, New York, NY 10011
Building
45 West 11th Street
Scope
Kitchen renovation, wall removal and electrical panel relocation
Timeline
Scoped at 5 to 7 weeks from commencement
Permits
Plumbing and electrical, pulled as part of the job
Completed
2022

The kitchen before the work

White cabinets, a granite counter, a marble-look tile backsplash and stainless appliances. Nothing was failing. What the kitchen had was a wall: it ended at the living area rather than opening into it, and the peninsula stopped where that wall began.

The original apartment before work, with a white kitchen, a peninsula with stools and a living area beyond
The original kitchen was white and closed off from the living area by a wall running to the right of the peninsula.
The original kitchen in white with a marble-look tile backsplash, stainless appliances and a granite counter
Not a kitchen in poor condition. Just one that stopped where the wall did.

The scope is unusually clear about timing, which is worth repeating because so few are. Work begins one to two weeks after the finishing materials are delivered, and the full scope is substantially complete five to seven weeks after that start. Materials first, then a start date, not the other way round.

What the crew did, in order

  1. Protect the route before touching the kitchen

    Hallways and common areas prepared as the building required and kept that way throughout, vents and exhaust access taped off including radiator connections, hallways cleaned at the end of each day with the Masonite lifted, and all garbage removed by whatever route the building allowed.

  2. Take out the wall, then make good properly

    The wall between the kitchen and the living area came out. It was not simply demolished: the scope specifies sheetrock, mud, tape and sand to finish, with miscellaneous light switches and outlets relocated as the new arrangement needed. That finishing sequence is the difference between an opening and a hole.

  3. Lift eighteen inches of wood floor

    To carry the kitchen tile out to the island, roughly eighteen inches of the existing wood flooring was removed at the boundary. The subfloor and concrete slab were then prepared and the tile laid across the extended area, so the floor change happens at the island rather than at the old wall line.

  4. Move the panel, then check the load

    The electrical panel was relocated up to three feet. The whole electrical scope is written as subject to confirmation by the electrician regarding the available electrical load for the apartment, which is the honest way to scope electrics in a pre-war building before anyone has opened anything.

  5. Run power out to the island through the column

    An island needs power and there is no wall to bring it from. A new 110 volt line was run out to the island through the column, which is why the island can carry an outlet without a cable crossing the floor. GFCI convenience outlets were run into the backsplash to the approved plan and the refrigerator line was relocated to suit the design.

  6. Replace the branch plumbing, rough for a dishwasher

    New hot and cold shut-off valves at two points, master and local, with new hot and cold lines and new waste and vent lines all run to the risers as branch replacements. The sink and faucet went back onto the existing rough, and a new rough was run for the dishwasher.

  7. Pull the permits

    Plumbing and electrical permits were pulled as a named line in the scope rather than assumed. On a job that moves a panel and replaces branch lines to the risers, that is not optional, and seeing it written down is a reasonable thing to ask for.

The finished kitchen

Navy shaker cabinets running to the ceiling with brass bar pulls, a white stone counter, and a handmade-look white square tile laid in a plain stacked pattern. The apartment door was painted in the same navy, so the entrance reads as part of the room rather than as an interruption.

The range wall with navy shaker cabinets, brass bar pulls, a stainless range and a tall refrigerator alongside
Cabinets run to the ceiling in navy. The brass pulls are the only warm metal in the room.
The kitchen looking toward the window, with the dishwasher, wall oven and microwave drawer set into the navy run
Every appliance sits inside the cabinet line, which is what lets the run read as joinery.
Close view of the sink wall with a matte black and brass faucet, white square tile and the dishwasher below
The backsplash is a handmade-look square tile with a soft glaze, set in a plain stacked pattern.

Five appliances were installed: a refrigerator, a gas range, a range hood, a dishwasher and a microwave. The scope also allowed for saving any appliances the client wanted reinstalled rather than replaced, which is worth having in writing before demolition rather than deciding on the day.

The kitchen from the entrance door, showing the counter run, the island beyond and the apartment door in navy
The apartment door was painted the same navy as the cabinets, which ties the entrance into the kitchen.
The sink and counter run with the refrigerator at the end and the range beyond
The refrigerator line was relocated to suit the new layout rather than the layout bending around it.

The island is the piece the wall removal paid for. It carries the counter, seating for two, and its own power. Against the navy and the white tile, the only other materials in the room are the brass of the pulls and the black of the sink and faucet.

The island and stools seen from the living area, with the kitchen behind and a hallway beyond
A new 110 volt line was run out to the island through the column, so the island has power of its own.
Close view of the black undermount sink, brass-accented faucet and white tile backsplash
The sink and faucet went back onto the existing rough. Only the lines feeding them were replaced.
Close detail of navy cabinet fronts with brass bar pulls against the pale floor tile
The tile floor was extended about eighteen inches into the old wood floor to reach the island.
Close view of the faucet against the white square tile, with the black sink below
Black, brass and navy against white tile. Four finishes, and no fifth.

Materials and finishes

Structure and floor

ElementSpecification
WallRemoved between kitchen and living area, then sheetrocked, mudded, taped and sanded
Wood flooringApproximately 18 in removed to extend the kitchen tile to the island
SubfloorExisting subfloor and concrete slab prepared for tile
Floor tileLaid in a standard pattern and grouted

Electrical

ElementSpecification
PanelRelocated up to 3 ft
LoadWhole electrical scope subject to the electrician confirming available apartment load
Island supplyNew 110V line run out to the island through the column
RefrigeratorExisting line relocated to the approved design
Backsplash outletsGFCI convenience outlets run to the approved plan
Ceiling lightNew fixture installed to the existing rough
Switches and outletsRelocated as the new layout required

Plumbing

ElementSpecification
Shut-off valvesNew hot and cold at two points, master and local
Water branch linesNew hot and cold, run to the risers
Waste and vent linesNew, run to the risers
Sink and faucetInstalled to the existing rough
DishwasherNew rough run
PermitsPlumbing and electrical permits pulled

Kitchen fit-out

ElementSpecification
CabinetsDoors, drawers, shelves, hinges and accessories, with crown and base moldings
Cabinet adjustmentDoors and drawers adjusted for fit and finish
CountertopTemplated on site, cabinets smoothed first, edge and sink mounting to selection
BacksplashWalls prepared, standard tile in a standard pattern, grouted and sealed if needed
AppliancesRefrigerator, gas range, range hood, dishwasher and microwave
Retained appliancesScope allowed for saving any the client wanted reinstalled
PaintWalls, ceiling, doors and trim primed, then two coats

The result

5 to 7weeks, as scoped
18 inof wood floor lifted for the tile
1wall removed

More MyHome projects in Manhattan

Questions this project answers

How long does a kitchen remodel take in a NYC apartment?

This one is scoped in two parts, which is the useful way to read any timeline. Work begins one to two weeks after the finishing materials are delivered, and the full scope is substantially complete five to seven weeks after that start. The material lead time sits outside the build window entirely, and it is where most of the slippage in apartment renovations actually happens. When a firm quotes you six weeks, ask whether that clock starts on the contract or on the delivery.

Can I take out the wall between my kitchen and living room?

Often, if it is not structural and your building agrees. This one came out, and the scope treats the making-good as real work rather than an afterthought: sheetrock, mud, tape and sand to finish, with light switches and outlets relocated as needed. There is a second consequence people forget, and this job names it: the floors on either side of a removed wall do not match. Here roughly eighteen inches of wood flooring was lifted so the kitchen tile could run out to the island and the change of material happens somewhere deliberate.

Can I put an outlet in a kitchen island?

Yes, and it usually needs planning before the floor goes down. On this job a new 110 volt line was run out to the island through the column, which is the tidy route when one exists. Where there is no column the alternative is a channel cut in the slab, which is a different order of work in a concrete-floored apartment building. If you want power on an island, raise it at design stage; it is close to impossible to add neatly afterwards.

My apartment trips a breaker whenever I use two appliances. Can that be fixed in a renovation?

Usually, and this scope shows the right first step: it makes the entire electrical section subject to the electrician confirming the available electrical load for the apartment. That is the honest sequence. You find out what the apartment can actually carry, then you design to it. Here the panel was relocated up to three feet as part of the work, the refrigerator line was moved to suit the new layout, and GFCI outlets were run into the backsplash to plan.

What are change orders, and how do I avoid being overcharged by my contractor?

A change order is a written amendment to what was agreed. The defences in this scope are worth copying. It names its dependency, making the electrical work conditional on a load check. It names its optionality, allowing for appliances to be saved and reinstalled rather than assuming everything is replaced. It names the permits it will pull, plumbing and electrical, rather than leaving them to appear later. And it separates the material lead time from the build window, so a late delivery does not silently become a late job.

Planning something like this?

MyHome has renovated apartments, co-ops, condos and townhomes across Manhattan and Brooklyn for more than 25 years. Complete the short questionnaire to start an estimate.

Let’s design your home together

Complete the short questionnaire to kick off your estimation process

Get an Estimate

Recent Projects

Just a moment...